Skip to content
Biviti
Talk to a Sage Intacct Expert

Construction

Keep every job’s economics connected, from estimate to final billing.

Construction finance lives at the job: budgets, commitments, change orders, progress billing, retainage and WIP. When the structure is right, finance, project managers and executives read the same numbers. When it is not, month-end becomes a reconciliation exercise.

Start with the kind of contractor you are.

Discovery begins with the organization type, because it changes the job structure, the billing, the payroll questions and the reports that matter.

General contractor

Subcontract commitments, owner billing, retainage in both directions and change orders flowing in from owners and out to subcontractors.

Change, Commitment, Cost, Billing, WIP, Forecast

One change order, followed through the job.

Step through Change, Commitment, Cost, Billing, WIP and Forecast. Each step updates the same job, so you can see which figures move and why.

Midway through an illustrative job: half complete on a cost-to-cost basis, and slightly overbilled.

What the design must decide

This is the starting point. Every later figure moves from here.

Illustrative job. Round numbers, no client data. Percent complete uses the cost-to-cost method, one of several methods a contractor may use. Retainage at 10 percent of billings.
Job measureValue at this step
Contract value1,000,000
Estimated cost at completion850,000
Committed cost600,000
Cost to date425,000
Percent complete50.0%
Earned revenue500,000
Billed to date540,000
Over or (under) billing40,000 over
Retainage receivable54,000
Forecast margin150,000
Backlog (contract not yet earned)500,000

The estimate, the project and the ledger must speak one language.

Job, phase, cost code and cost type are the spine of construction reporting. If the estimate, the project management structure and the accounting cost codes do not align, integration becomes complex and job reports become hard to reconcile.

Estimate

  • Assemblies and items
  • Quantities
  • Unit costs

Project system

  • Job and phase
  • Budget lines
  • Commitments and changes

Sage Intacct

  • Job and phase
  • Cost code and cost type
  • Budget, actual and committed

Cost types to agree

  • Labour
  • Materials
  • Equipment
  • Subcontract
  • Other direct cost

Original budget

The estimate as awarded, kept unchanged for comparison.

Approved revisions

Changes that moved budget with a recorded approval.

Pending changes

Exposure that is known but not yet approved, reported separately so it is never lost or double counted.

Contracts decide how revenue is earned and billed.

One agreed price for defined work. Revenue is earned as the job progresses, so the estimate at completion drives margin.

Design

Percent-complete method, change order discipline and forecast reviews.

Progress billing, including AIA-style schedules of values, bills against work completed. Unapproved change exposure should be visible beside it.

Retainage, in both directions

Retainage receivable
Held back by the owner from your billings, released at agreed milestones or completion.
Retainage payable
Held back by you from subcontractor invoices, released under the subcontract terms.

Sage announced retainage enhancements as generally available in its August 2026 Sage Intacct release, and New Construction Billing as an Early Adopter release in the United States, United Kingdom, Australia and Canada. Biviti validates each billing and retainage requirement against what is currently available in your region.

WIP, explained in four lines.

The work-in-progress schedule compares what has been earned with what has been billed. Finance, project managers and executives need to agree how each line is calculated, who owns the estimates, and how often it is reviewed.

  1. Percent complete=Cost to date ÷ Estimated cost at completion
  2. Earned revenue=Percent complete × Contract value
  3. Over or underbilling=Billed to date − Earned revenue
  4. Profit fade=Change in forecast margin between reviews

Overbilling

Billed ahead of the work. A liability: cash has arrived for work not yet performed.

Underbilling

Work performed but not yet billed. An asset, and often an early sign of cash pressure or an optimistic estimate.

Cost to complete

The project manager’s estimate of remaining cost. It drives everything above, so it needs an owner and a review cadence.

Projected losses

Agree with your accountants how a projected loss is recognized, and make sure the WIP review surfaces it early.

Backlog

Contract value not yet earned. With margin, it is the forward view executives and lenders ask for.

Project profitability

Margin by job, by project manager and by contract type, against the original estimate.

Field to finance: decide who owns what.

Field and project platforms, such as Procore, estimating, time capture and service systems, all touch finance. Integration moves data. It does not decide ownership. Each record needs one system of record, agreed before anything is connected.

RecordWhy it mattersDecision
VendorOften created in finance and shared outward.Agree the owner
JobSet up once, in one system, then shared.Agree the owner
Cost codeMust match the estimate and the project structure.Agree the owner
CommitmentFrequently issued from the project system.Agree the owner
Change orderNeeds one status everyone trusts: pending, approved or rejected.Agree the owner
InvoiceApproved by the project team, posted by finance.Agree the owner
Payment statusPaid from finance, visible to project managers.Agree the owner

Payroll architecture

Construction payroll can involve unions, certified payroll, prevailing or varying rates and labour allocated to jobs and cost codes. Biviti validates the payroll architecture for each requirement, including which system calculates pay and how labour cost reaches the job, rather than assuming every scenario is handled natively.

Open jobs are not closed history.

Migrating an active job is a design decision, not a data load. Every open job needs agreed figures at the cutover date, reconciled before go-live.

  1. Original contract value
  2. Approved changes and revised contract
  3. Pending changes and their exposure
  4. Current budget by cost code
  5. Actual cost to date
  6. Open commitments and remaining amounts
  7. Billed to date and retainage held
  8. WIP position at the cutover date
  9. How much transaction history to bring, and in what detail

Questions to answer before configuration.

  1. Do your estimate, project system and accounting cost codes follow the same structure?
  2. Who owns cost to complete, and how often is it reviewed with finance?
  3. Which system issues commitments and change orders today?
  4. How are retainage receivable and payable tracked and released?
  5. Which payroll scenarios apply: unions, certified payroll, multiple rates, job allocation?
  6. How many jobs will be open at cutover, and what figures must convert for each?

Book a meeting

Online scheduling is not available right now. Email hello@biviti.com or call 403-879-5828 to arrange a time.